Functional Topic
Procurement Governance, Contract Strategy & Commercial Rate Benchmarking
Industry
Energy & Utilities
Support Needed
Independent Commercial Assessment & Contracting Strategy (pre-RFP)
Duration
10 Weeks
A major U.S. electric utility was approaching a 2026 renewal of its overhead-construction contracts. Its unit-rate book — the rate catalogue governing how contractors bill — had not been refreshed in five years, unit billing ran well below industry norms, and there was no competitive-tension mechanism, leaving an unquantified above-market exposure heading into the RFP. Leadership needed to:
I led the independent assessment end to end — designing the three-layer method, analysing 12 months of approved spend ($233M across 565,505 transactions, 482 rate-book items, six contractors), quantifying above-market exposure and isolating its structural root cause, and building the five-pillar contracting framework and phased roadmap.
Pareto of the $233M portfolio · Illustrative
So what: the governance problem is highly concentrated — 45 items, not 482 — which makes it operationally addressable rather than overwhelming.
Bubble size = share of spend; an item is critical only when both axes are high · Illustrative
So what: high spread alone isn't the risk — exposure concentrates where spread and utilisation are both high, so the fix is targeted, not portfolio-wide.
Unit-billing variance vs. weighted-average rate · contractors anonymized · Illustrative
So what: the two largest contractors carry ~55% of the exposure — but the driver is the absence of rate enforcement, not contractor choice, so the same billing would recur with any replacement.
Concentrated
45 of 482 rate-book items drove ~80% of the $233M — the governance issue is highly concentrated and operationally addressable.
Root cause
The two largest contractors carried ~55% of variance, but the cause was the absence of rate enforcement — replacements would reproduce it.
Ungoverned spend
$22.4M of cost-plus spend sat outside any usage framework, letting unit rates act as effective floors and absorbing all crew-time overruns.
Rate renegotiation alone will not hold — without structural contract reform, contractors revert to misusing ambiguous rate descriptions in the next cycle. The five-pillar framework converts an indicative opportunity into a permanently governed programme, making rate improvements auditable and durable through the 2026 renewal and beyond.
Illustrative & anonymized. Client and contractor identities withheld; all three charts are directional, built to demonstrate the analytical method rather than report exact figures.